Area: Clareen
Started: December 1954
Finished: April 1955
Poles used: 754
Line used (km): 73
Premises connected: 15
The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.
The REO News from August 1955 tells us that the weather caused the biggest problem in Clareen