Rural electrification of Liskeevy, Co Galway in 1956

Area: Liskeevy
Started: September 1955
Finished: February 1956
Poles used: 670
Line used (km): 68
Premises connected: 90

Liskeevy-Map-GALWAY-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

Bad weather, bog and rock were encountered in Liskeevy according to The REO News from May 1956Liskeevy-REO-News-May-19560016